SINGAPORE – Singapore has agreed to Malaysia’s request for an additional one-month suspension of the Rapid Transit System (RTS) project in the spirit of bilateral cooperation, and also agreed to waive additional costs incurred during the period, said a Ministry of Transport (MOT) spokesman.
But Singapore reserves the right to claim any additional costs incurred beyond Sept 30, should Malaysia request any further extensions of the suspension period, which will now end on Oct 31.
Both governments signed a bilateral agreement last year to build the 4km cross-border MRT link from Woodlands in Singapore to Bukit Chagar in Johor to help alleviate congestion on the Causeway.
But in March, Malaysia requested a six-month extension to respond to Singapore on issues relating to the RM4 billion (S$1.3 billion) project. Then in May, both countries agreed to suspend work on the RTS link until Sept 30.
As part of the deal, Malaysia agreed to reimburse Singapore more than $600,000 for abortive costs incurred as a result of the six-month suspension.